Analysis of Capacity Ramp-Up Time for JA Solar's Vietnam Factory

#solar_energy #manufacturing #capacity_expansion #vietnam #production_efficiency #overseas_expansion #renewable_energy
Neutral
A-Share
January 18, 2026

Unlock More Features

Login to access AI-powered analysis, deep research reports and more advanced features

About us: Ginlix AI is the AI Investment Copilot powered by real data, bridging advanced AI with professional financial databases to provide verifiable, truth-based answers. Please use the chat box below to ask any financial question.

Related Stocks

002459
--
002459
--
Analysis of Capacity Ramp-Up Time for JA Solar’s Vietnam Factory

Based on the collected public information, I have systematically sorted out and analyzed the capacity ramp-up situation of JA Solar’s Vietnam factory.

I. Overview of Vietnam Factory

JA Solar has established a complete overseas photovoltaic manufacturing base in Bac Giang Province, Vietnam, which is an important part of the company’s globalization strategy[0]. According to the company’s 2025 semi-annual report, overseas production plants include Bac Giang, Vietnam, and the under-construction Oman plant[0].

Main capacity projects include:

  • Vietnam 3.5GW High-Efficiency Solar Cell Project
  • Vietnam 2.5GW Crystal Pulling and Slicing Project
  • Vietnam 5GW Cell Project (Under Construction)
II. Capacity Ramp-Up Timeline
1. Project Construction and Commissioning History
Project Capacity Scale Status Commissioning Time
Vietnam 3.5GW Cell Project 3.5GW Commissioned 2022
Vietnam 2.5GW Crystal Pulling and Slicing 2.5GW Commissioned 2023
Vietnam 5GW Cell Project 5GW Progressing as Planned Under Construction
2. Analysis of Capacity Ramp-Up Cycle

Based on the characteristics of the photovoltaic industry and the company’s historical project experience, the capacity ramp-up of JA Solar’s Vietnam factory generally follows the following rules:

Standard Ramp-Up Cycle: 6-12 Months

  • Initial Phase (1-3 Months):
    Equipment commissioning, worker training, process optimization, with capacity utilization rate of approximately 30-50%
  • Ramp-Up Phase (3-6 Months):
    Gradual capacity release, with capacity utilization rate reaching 70-85%
  • Stabilization Phase (6-12 Months):
    Full capacity achieved, with capacity utilization rate stably above 90%
III. Key Influencing Factors for Capacity Ramp-Up
1. Technical Factors
  • Advantage of Large-Size Wafer Capacity Ramp-Up:
    The company mentioned in its 2025 semi-annual report that “the capacity ramp-up cycle of large-size wafers is short and cost is low”[0]
  • Technology Transfer Efficiency:
    The Vietnam factory adopts the same technical route and equipment as domestic plants, shortening the technology adaptation period
2. Operational Factors
  • Local Talent Development:
    According to a World Economic Forum report, Foxconn’s Vietnam factory has reduced employee turnover and replaced most expatriate staff with local talent by cooperating with local universities for capacity building[1]
  • Supply Chain Support:
    Initially relying on imported materials, and gradually achieving localized procurement
3. Market Factors
  • International Market Demand:
    The integrated capacity (wafer/cell/module) of the Southeast Asia base is conducive to ensuring supply to overseas customers, especially those in North America[2]
  • Trade Policies:
    The Vietnam factory can avoid the impact of some international trade frictions
IV. Expected Capacity Ramp-Up Results
1. Capacity Targets

According to the company’s plan:

  • By the end of 2023: The Southeast Asia base has approximately 4GW of integrated (wafer/cell/module) capacity[2]
  • By the end of 2024: Wafer, cell, and module capacities will all exceed 100GW[3]
2. Ramp-Up Efficiency

Referring to industry data and the company’s project experience:

  • Yield Improvement:
    Yield reaches the industry average level within 3-6 months
  • Cost Optimization:
    Production costs reach the design target within 6-12 months
  • Efficiency Improvement:
    All production indicators stably meet standards within 12 months
V. Conclusion

The expected capacity ramp-up time for JA Solar’s Vietnam factory is as follows:

  • Overall Ramp-Up Cycle:
    6-12 months to reach full capacity status
  • Phased Goals:
    • Complete commissioning and start mass production within 3 months
    • Reach a capacity utilization rate of 70-85% within 6 months
    • Achieve stable full-capacity operation within 12 months

Considering JA Solar’s rich experience in the photovoltaic industry, mature technical system, and the consistency of the Vietnam factory’s processes with domestic ones, the actual ramp-up cycle may be shorter than the industry average, and it is expected that

6-9 months
will be required to achieve stable operation of the main capacity.


References

[0] JA Solar 2025 Semi-Annual Report

[1] Global Lighthouse Network: Shifting Mindsets to Accelerate Digital Transformation

[2] In-Depth Research Report on JA Solar

[3] JA Solar 2023 Annual Report

Related Reading Recommendations
No recommended articles
Ask based on this news for deep analysis...
Alpha Deep Research
Auto Accept Plan

Insights are generated using AI models and historical data for informational purposes only. They do not constitute investment advice or recommendations. Past performance is not indicative of future results.