Analysis of Construction Progress and Financial Impact of Sanbo Brain Hospital's New Campuses

#hospital_expansion #healthcare_services #neurology #medical_construction #capital_expenditure #profit_decline #shenzhen_stock #growth_investment
Mixed
A-Share
January 18, 2026

Unlock More Features

Login to access AI-powered analysis, deep research reports and more advanced features

About us: Ginlix AI is the AI Investment Copilot powered by real data, bridging advanced AI with professional financial databases to provide verifiable, truth-based answers. Please use the chat box below to ask any financial question.

Related Stocks

301293
--
301293
--

Based on the latest information I have collected, the following is a detailed update on the construction progress of each new campus of Sanbo Brain Hospital:

Overview of Construction Progress of Sanbo Brain Hospital’s New Campuses
1. Beijing Dongba New Campus (Final Construction Stage)

Construction Progress:

  • Floor Area:
    63,000 square meters [0][1]
  • Planned Beds:
    480 (the existing Beijing Sanbo old campus has 256 beds) [2]
  • Latest Status:
    Has obtained medical practice license, in the final construction stage [1][2]
  • Expected Operation Time:
    Commence operations in Q1 2026 [2]

Facility and Equipment Upgrades:

  • Number of class 100 clean operating rooms increased from 6 to 13 [2]
  • Introduced high-end 3.0T MRI [2]
  • 96-channel magnetoencephalography (MEG) equipment [2]
  • Imported ROSA surgical robot [2]
  • Imported electroencephalogram (EEG) detection system [2]

Strategic Positioning:

The new campus is positioned as a “large specialist, small general” hospital with neurological specialties as its core. Based on existing disciplines, it will focus on developing emergency medicine, critical care medicine, pain management, rehabilitation medicine, and traditional Chinese medicine departments [2]


2. Kunming Sanbo New Campus (Already in Operation)

Construction Progress:

  • Relocation Time:
    Officially relocated to the new campus in May 2025 [3][4]
  • Planned Beds:
    200 [2]
  • Operation Status:
    Already in operation, with a significant increase in business volume compared to the old campus [3]

Newly Added Facilities and Disciplines:

  • Added cardiology department [3]
  • Purchased medical linear accelerator [3]
  • Gamma knife equipment [3]
  • Hyperbaric oxygen chamber and other large-scale medical equipment [3]
  • Significant improvement in hospital environment [3]

3. Xi’an Sanbo New Campus (Early Operation Ramp-Up Phase)

Construction Progress:

  • Opening Time:
    Officially opened for operation in September 2025 [3][4]
  • Planned Beds:
    200 [2]
  • Operation Status:
    Currently in the ramp-up phase [3]

Current Challenges:

  • Still requires time for market cultivation [3]
  • Patient referral efforts are ongoing [3]
  • Current patient volume and ward occupancy rate have not yet reached full capacity [3]

4. Financial Impact Analysis

Performance Data (First Three Quarters of 2025):

Indicator Value Year-on-Year Change
Total Operating Revenue RMB 1.273 billion ~20% year-on-year increase
Net Profit Attributable to Parent Shareholders RMB 83.6282 million 20.01% year-on-year decrease
Q3 Single-Quarter Net Profit RMB 13.93 million 63.26% year-on-year decline

Impact of Construction Investment:

  • The company’s interest-bearing liabilities surged to RMB 375 million, representing a year-on-year increase of over 500% [1]
  • Before the new campuses generate large-scale revenue, pre-operation investments will continue to impact profit performance [1]

5. Group-Wide Bed Capacity Plan

Bed Layout of the 9 Existing Hospitals (After the Beijing Dongba New Campus Commences Operations):

Campus Number of Beds
Beijing Sanbo Old Campus 256
Beijing Sanbo Dongba New Campus 480
Kunming Sanbo 200
Fujian Sanbo 300
Chongqing Sanbo Jiangling 400
Chongqing Sanbo Chang’an 486
Henan Sanbo 160
Luoyang Sanbo 260
Chengdu Dongli 502
Xi’an Sanbo 200
Total
2,988

Summary

Sanbo Brain Hospital is currently in the

phase of concentrated construction and early operation of multiple campuses
. The Kunming Sanbo New Campus has successfully relocated and achieved increased business volume; the Xi’an Sanbo New Campus has just opened and is in the market cultivation phase; the Beijing Dongba New Campus has completed main construction and is expected to officially commence operations in Q1 2026. Overall, the company adopts a
“heavy-asset, long-cycle”
expansion model. The concentrated construction of new campuses creates certain short-term pressure on performance, but in the medium to long term, it will significantly enhance the company’s medical service capabilities and market coverage.


References

[0] Sina Finance - Brain-Computer Interface Concept Surges, Sanbo Brain Hospital’s Stock Price Doubles (https://finance.sina.com.cn/jjxw/2026-01-17/doc-inhhqpcz4801027.shtml)

[1] Guancha.cn - Brain-Computer Interface Concept Surges, Sanbo Brain Hospital’s Stock Price Doubles (https://user.guancha.cn/main/content?id=1585212&s=fwtjgzwz)

[2] Securities Times Network - Sanbo Brain Hospital Interactive Q&A (https://www.stcn.com/quotes/index/sz301293.html)

[3] Securities Times Network - Sanbo Brain Hospital Investor Q&A (https://www.stcn.com/quotes/index/sz301293.html)

[4] Securities Times Network - Operation Status of New Campuses (https://www.stcn.com/quotes/index/sz301293.html)

Related Reading Recommendations
No recommended articles
Ask based on this news for deep analysis...
Alpha Deep Research
Auto Accept Plan

Insights are generated using AI models and historical data for informational purposes only. They do not constitute investment advice or recommendations. Past performance is not indicative of future results.